With fall in full swing, our construction sites remain a hive of activity. Across our portfolio, over $1.5 billion worth of projects are under development and steadily taking shape. Driven by our dedication to excellence and quality, here’s an update on the latest milestones.
Burke – Toronto
Burke, a 53-storey tower, is making impressive progress in Toronto’s vibrant St. James Town neighbourhood. Concrete forming has now reached level 43, while window installation has advanced to level 25 and precast installation is complete up to level 29. Interior framing is underway on level 20, with drywall installation progressing to level 17. Electrical and mechanical installations continue, with in-home progress reaching level 18. Interior finishes are advancing through level 10, and exterior wall waterproofing is ongoing. Curtain wall installation has begun on the ground and second floors, and mechanical and electrical rough-ins are progressing in the amenity areas. Main elevator installation continues as planned, and parking elevators are now fully completed.
Myriad – Coquitlam
Myriad, the final phase of The Heart of Burquitlam master-planned community, has reached new heights, officially topping off in September 2024. The residential window installation is now finished, while the curtain wall is being installed on level 50. Inside, steel stud framing has advanced to level 47, and suite mechanical and electrical rough-ins are progressing to levels 45 and 44, respectively. Sprinkler rough-ins have now reached level 43, while drywall installation is advancing to level 39. Interior finishes are steadily progressing, with doors and trim on level 34, tile work on level 31, cabinetry on level 29, vinyl flooring on level 27 and appliance installation reaching level 23. Balcony railings have been installed up to level 25, and elevator lobby work is advancing on level 9.
North Harbour – North Vancouver
North Harbour is transforming North Vancouver’s waterfront with a blend of condominium homes, rental apartments, retail spaces and vibrant amenities. Each building is progressing as scheduled, contributing to the area’s dynamic evolution.
- Drift: Drywall installation is complete, with tiling progressing to level 8 and cabinetry installation reaching level 7. Flooring is advancing on level 6, and countertop installation is underway on level 5. Mechanical and electrical finishes are progressing on level 3.
- Aire East: Floor layout has reached level 7, with drywall framing progressing from levels 4 to 6. Mechanical rough-ins are advancing on level 3, electrical rough-ins on level 2 and hydronic pipes and drains are in progress on level 1.
- Aire West: Taping and sanding are progressing on level 7, with drywall boarding on level 6. Tiling is prepared for installation on level 4, and cabinet installation has begun on level 3.
- Rental: Drywall installation is complete, with tiling progressing to level 9 and cabinetry advancing on levels 7 and 8. Flooring installation is ongoing on levels 5 and 6, while countertop installation is underway on level 4. Terra cotta cladding on the exterior is also progressing.
- North Harbour Infrastructure: Civil infrastructure work continues to support the overall development, ensuring smooth integration of all project components.
As we advance through autumn, we’re excited to reach new milestones and look forward to sharing further progress as these exceptional communities come to life.